Ho Chi Minh City consider shortening investment procedures for construction of commercial housing projects


On May 5, Mr. Le Hoang Chau, Chairman of the HCM City Real Estate Association (Horea), said Mr. Le Hoa Binh, Vice Chairman of the City People’s Committee, and leaders of departments and sectors chaired the meeting with Horea on the implementation of Decree 30/2021 / ND-CP, Decree 31/2021 / ND-CP, Decree 148/2020 / ND-CP and guiding the implementation of construction investment procedures for the project. commercial housing project in Ho Chi Minh City.

Ho Chi Minh City considers shortening the investment procedures for the construction of a commercial housing project (Artwork from the Internet)

Accordingly, Vice Chairman of the People’s Committee of Ho Chi Minh City Le Hoa Binh asked departments and branches to consider unanimously the contents to submit to the City People’s Committee, to guide the implementation of construction investment procedures for commercial housing projects in the area. table. As follows:

Step 1: The Department of Planning and Investment implements the procedure of “approval of investment policy concurrently with investor approval” for commercial housing projects with land use rights, in accordance with the Law on Investment 2020 and Decree Decree 31/2021 / ND-CP (with the name “investor”).

Step 2: The Department of Planning and Architecture or the People’s Committee of Thu Duc City, the districts – districts implement the procedure “approving the detailed planning of 1/500 scale, or the master plan plan” commercial housing project has written ” approval of investment policy concurrently with investor approval “, according to the provisions of the Law on Urban Planning 2009, the Construction Law (amended) 2020 (stipulating that” the investor is the investor can be authorized by the housing authority). Authorized country for approval “).

At the same time, the Department of Planning and Investment was assigned to chair working with departments and branches within 1 week, agreeing the content of the next administrative procedures to submit to the People’s Committee of Ho Chi Minh City for approval, guiding the consistent implementation above. locality. On the basis of the contents agreed with the departments and branches, Horea would like to propose the next steps and procedures.

Step 3: The Department of Natural Resources and Environment implements the procedures for land allocation or change of the purpose of land use, in accordance with the 2013 Law on Land.

Step 4: Department of Construction implements basic design appraisal procedures; Construction license; At the same time, the Department of Natural Resources and Environment and the Department of Finance shall carry out the procedures to determine the financial obligations, land use fees and notify the investor for implementation.

Horea suggested the Department of Planning and Investment and related departments and branches to set the time for each administrative procedure to be announced for investors to jointly implement. Horea also requested the Department of Planning and Investment and other departments and branches to submit to the City People’s Committee for guidance on implementation of construction investment procedures for social housing projects in the area.

Previously, Horea has submitted a petition to urgently remove the “bottleneck” of procedures to identify the investor of all commercial housing projects and social housing projects.

In particular, Horea said that the big “problems” for the congestion of procedures for identifying investors of all commercial housing projects and social housing projects stemmed from a number of articles in Decree 99, It is necessary to soon be considered by the competent state agency and have solutions to handle it.